71 Projects. Click [View] for details.
| | Project Number | Application Type | Applicant(s) | Landowner(s) | Project Addres | Description | Status | Town | Hearing Date | Decision Issued | Agenda Date | Comment/Petition due by |
|
|
1R0975-4
|
|
Kenneth Mohan;
|
Kenneth Mohan;
|
Town Farm Road/Blackberry Lane
|
Based on an initial, informal jurisdictional review of a boundary line adjustment survey prepared
for the intended transfer of 1.3-acres of land from the permitted parcel to an adjoining
landowner, application 1R0975-4 was submitted on November 12, 2025, for recordkeeping
purposes of the transaction. An incompleteness letter was issued by the District 1 Coordinator
on November 25, 2025. The application fee payment, determined to be incorrect, was voided
and returned to Applicant on December 1, 2025.
Subsequent to that, jurisdictional opinion JO 1-524 was issued on May 4, 2026, deeming
reclamation complete on the permitted parcel in accordance with conditions 4, 5, and 6 of Land
Use Permit 1R0975-3.
Pursuant to the further analysis and conclusion rendered in JO 1-524, application 1R0975-4
was no longer required and was therefore able to be withdrawn by Applicant. Applicant filed a
withdrawal request on May 5, 2026.
Application 1R0975-4 is deemed withdrawn.
|
Withdrawn
|
Brandon
|
|
Yes
|
05-11-2026
|
|
|
|
1R0975-5
|
|
Kenneth Mohan;
|
Kenneth Mohan;
|
Town Farm Rd/Blackberry Lane
|
Subdivision and sale of a 4.2 acre parcel
|
Withdrawn
|
Brandon
|
|
Yes
|
05-11-2026
|
|
|
|
8B0305-1
|
|
Spencer Bloom;
|
Spencer Bloom;
|
LOT 4 HAVOC HILL
|
Application 8B0305-1 from Spencer Bloom was received on May 21, 2025. The project is generally described as relocation of a previously permitted single-family home and wastewater system located on “Lot 4” of an existing residential subdivision. Application 8B0305-1 was never deemed complete and therefore is not under the jurisdiction of the District 8 Environmental Commission .
The application was determined to be incomplete under Act 250 Rule 10(D) for reasons stated in a letter from the District Coordinator to the Applicant dated May 27, 2025. On May 7, 2026, the Applicant (through their engineer, Christopher M. Ponessi of Mance Engineering Partners, P.C.) submitted a request that the application be withdrawn.
The purpose of this Memorandum is to acknowledge receipt of the withdrawal request (included as Exhibit 015 in the online application file) and document that application 8B0305-1 has been withdrawn.
|
Withdrawn
|
Dorset
|
|
Yes
|
05-11-2026
|
|
|
|
7C0929-2
|
Adm. Amend
|
JKO Properties LLC;
|
JKO Properties LLC;
|
454 VT Route15W
|
Proposed 12ftx10ft building addition to the existing convenience store for a new beverage cooler.
|
Permit
|
Hardwick
|
|
Yes
|
05-18-2026
|
|
|
|
5W1410-1
|
Adm. Amend
|
Daniel Beede; Kaylie Viens;
|
Daniel Beede; Kaylie Viens;
|
2293 North Fayston Rd. Fayston, VT 05660
|
This permit specifically authorizes the construction of a 16 foot by 12 foot shed next to the existing residence. The shed's primary use is for personal items such as a lawn mower, kayaks, and tires.
|
Permit
|
Fayston
|
|
Yes
|
05-18-2026
|
|
|
|
8B0623-1A
|
Adm. Amend
|
Jeffrey Nyweide;
|
Jeffrey Nyweide;
|
507 Benson Road
|
Pursuant to a timely request for extension to the construction completion deadline, this
permit specifically authorizes the extension of the construction completion date from
October 15, 2025, to October 15, 2029. No other changes to the project are proposed or
authorized herein.
The project is located at 507 Benson Road (aka Boorn Brook Farm), in Manchester, VT.
|
Permit
|
Manchester
|
|
Yes
|
05-11-2026
|
|
|
|
2W1316-1B
|
Adm. Amend
|
Green Mountain Land Development and Gravel Company, Inc;
|
|
Forrester Rd
|
CCDE
|
Dismissed
|
Jamaica
|
|
Yes
|
05-25-2026
|
|
|
|
4C1203-3
|
Adm. Amend
|
Argosy Holdings LLC;
|
Argosy Holdings LLC;
|
950 Route 7 South
|
This permit specifically authorizes installation of two (2) truck EV charger islands with pavement expansion to accommodate truck EV chargers (the “Project”). The Project is located at 950 Route 7 South in Milton, Vermont.
|
Permit
|
Milton
|
|
Yes
|
05-11-2026
|
|
|
|
5L0822-21
|
Adm. Amend
|
Courtney & Michael Bonanno;
|
Courtney & Michael Bonanno;
|
95 Francis Lane
|
This permit specifically authorizes the construction of a 4-bedroom single-family home on Lot # 1-4 of Parcel 1B in the Stowe Club Highlands subdivision. (Originally approved under Land Use Permit 5L0822-19, issued on September 9, 2014). The lot, located at 95 Francis Lane, is served by municipal water and an on-site wastewater disposal system.
|
Permit
|
Stowe
|
|
Yes
|
05-18-2026
|
|
|
|
5W0431-12A,5W1012-3A
|
Adm. Amend
|
State of Vermont - VT BGS;
|
State of Vermont - VT BGS;
|
No E991 Address - Off of Randall Street
|
This permit specifically authorizes the subdivision of 54.8-acre Parcel 19-325 into two lots. Lot A will be 49.3 acres, and lot B will be 11.8 acres and includes portions of the Waterbury Complex parking area. This subdivision is exempt from water & wastewater permit 1-304(4) in that Parcel 19-325 is unimproved and will remain such.
|
Permit
|
Waterbury
|
|
Yes
|
05-11-2026
|
|
|
|
JO 1-524
|
JO
|
|
|
247 Blackbery Lane (off Town farm Rd)
|
Jurisdictional request with respect to whether the conditions required for reclamation of a gravel pit were met, such that the project and project tract are no longer subject to Act 250 jurisdiction.
|
JO issued
|
Brandon
|
|
Yes
|
05-11-2026
|
|
|
|
JO 1-525
|
JO
|
|
|
SPAN 384-119-12471
|
The Project consists of the construction and operation of a 129-room hotel on an approximately 7.50-acre parcel in Mendon, Vermont (SPAN 384-119-12471). The hotel will be a commercial lodging facility operated under a national franchise agreement, serving the traveling public on a transient, fee-based basis. The Project will be constructed on a single, lawfully existing parcel. There is no phased or coordinated development proposed on adjacent lands, and the Applicant does not own or control other parcels that would be aggregated with this Project for Act 250 jurisdictional purposes.
|
JO issued
|
Mendon
|
|
Yes
|
05-11-2026
|
|
|
|
JO 1-526
|
JO
|
|
Linda & John Calotta;
|
1675 Eastham Road
|
Project: replacement barn to be located and constructed at 1675 Eastham Road,
Shrewsbury (SPAN #594-187-10094) to support Agricultural and Forestry Uses at 1675
Eastham Road in Shrewsbury, VT, and on the adjacent 75-acre parcel owned by a related
company (SPAN # 594-187-10894) and on another nearby 73-acre parcel owned by
another related company (SPAN # 594-187-10330)
|
JO issued
|
Shrewsbury
|
|
Yes
|
05-18-2026
|
|
|
|
JO 2-375
|
JO
|
|
Divided Sky Foundation;
|
262 Fox Lane
|
Scope of work as follows: Provide a new ADA platform lift at studio entrance and rework the walls surrounding the space as required. Additionally reinforce/repair the floor below to support the ADA lift. Remove/replace the sprinkler head as required below the platform floor. Remove the existing exterior stairs & railings along with loading dock stairs and replace with new ones. Remove the existing roof on the loading dock shed. New steel columns with concrete bases and a new CMU foundation wall & concrete ramp. New wood beams and roof and the installation of new exterior windows at existing openings. Painting repair as needed and trim/siding repair as needed. The Project is further described in the JO request and exhibits (Project Number JO 2-375 on the Act 250 Database online).
|
JO issued
|
Ludlow
|
|
Yes
|
05-11-2026
|
|
|
|
JO 3-425
|
JO
|
|
Town of Bethel;
|
Cemetery Rd and Town Highway 97
|
replacing the existing watermain on the north side of Route 107, between Cemetery Road and Town Highway 97. The 2" galvanized steel will be replaced with a 4" PVC line. Horizontal directional drilling or open trench excavation is expected. The total length of the project is roughly 1,500 linear feet. All work is expected to be within the Route 107 road right-of-way.
|
JO issued
|
Bethel
|
|
Yes
|
05-11-2026
|
|
|
|
JO 3-426
|
JO
|
|
|
6886 Vermont Rte 125
|
fix a broken overflow culvert on our snowmaking pond which is causing bank
erosion.
|
JO issued
|
Hancock
|
|
Yes
|
05-18-2026
|
|
|
|
JO 3-428
|
JO
|
|
|
38 Farnsworth Rd.
|
rehabilitation of a vacant historic building.
|
JO issued
|
Braintree
|
|
Yes
|
05-25-2026
|
|
|
|
JO 4-524
|
JO
|
|
|
|
The University of Vermont (UVM) Miller Research & Educational Center (the Center), a working farm, includes a ~17,200 square foot (SF) pond previously used for farm irrigation. The Center no longer needs or utilizes the water in this pond for irrigation and would like to fill it in in order to create more agricultural pastureland.
|
JO issued
|
Burlington
|
|
Yes
|
05-11-2026
|
|
|
|
JO 4-527
|
JO
|
|
Burlington Congregation of Jehovah’s Witnesses; Phillip Benjamin Burlington Congregation of Jehovah’s Witnesses Inc.;
|
610 Main Street
|
Demolition to slab of existing structure and reconstruction of same size (4,900 sf) structure on the existing slab, connecting to existing utilities. The lower parking lot will be paved with pedestrian sidewalks installed along the front of the building. Signage and lighting against the building will be updated. No additional signage or light poles will be installed and resulting lighting will not be brighter than existing. Only the existing developed areas (totaling 15,185 sf) of the 3.5 acre parcel will be disturbed. There will be no additional site work, tree removal, or landscaping besides reseeding disturbed areas from construction traffic. The Project is further described in the JO request and exhibits (Project Number JO 4-527 on the Act 250 Database online).
|
JO issued
|
Colchester
|
|
Yes
|
05-25-2026
|
|
|
|
JO 4-528
|
JO
|
|
Housing Foundation, Inc.; Tyler Maas Vermont State Housing Authority;
|
|
Construction of stormwater management facilities to comply with the three-acre site requirements of the Stormwater Permitting Rule. The project is a revision to the project reviewed in JO 4-444.
|
JO issued
|
Bolton
|
|
Yes
|
05-25-2026
|
|
|
|
JO 4-529
|
JO
|
|
Jason Adams Adams Real Properties, LLC;
|
35 Caroline Court
|
Proposed construction of a single family residence and municipal sewer and water connections on Lot 1 of a project approved in 2020 for a daycare facility on this lot. The daycare was never constructed. The landowner is Adams Real Properties, LLC.
|
JO issued
|
Williston
|
|
Yes
|
05-18-2026
|
|
|
|
JO 4-530
|
JO
|
|
Doug Boardman Larkin Hospitality;
|
1702 Shelburne Road (151 Larkin Way)
|
Conversion of the Smart Suites motel (formerly known as both Comfort Suites, and Staybridge Suites) located at 1702 Shelburne Road (151 Larkin Way) in South Burlington, Vermont to 51 units of permanently affordable housing. The project tract is subject to Act 250 land use permit series 4C0526, specifically 4C0526-10 and amendments. 11 of the units will satisfy the definition of “affordable housing” under 24 V.S.A. § 4303(1).
|
JO issued
|
South Burlington
|
|
Yes
|
05-11-2026
|
|
|
|
JO 4-533
|
JO
|
|
Dylan Corr;
|
25 School Street
|
Construction of a new primary residential dwelling (multi-family triplex), containing three two-bedroom apartments, one attached garage and one accessory storage shed. Two of the apartments will be approximately 1,600sf, and one of the apartments will be approximately 1,100sf, located above the garage. The garage will be approximately 1,100sf, and the shed will be approximately 380sf. The project parcel is 4.08 acres and will not be subdivided. The landowner has not constructed other housing units within the past five years.
|
JO issued
|
Milton
|
|
Yes
|
05-25-2026
|
|
|
|
JO 5-213
|
JO
|
|
Chase Rosenberg 18 Clark LLC; Chris Howell 18 Clark LLC; Graham Mink Mink Properties LLC;
|
18 Clark Avenue
|
10 Unit Apartment building converted the duplex zoned building into 10-units with no local, or Act 250 permits, except for permits for the sprinkler system.
|
JO issued
|
Morristown
|
|
Yes
|
05-25-2026
|
|
|
|
JO 5-230
|
JO
|
|
Kelly Gleason Casella Waste Management Inc.;
|
1855 VT Route 100
|
The project will involve the replacement of an existing approximate 34-foot long by 10-foot wide truck scale with a 70-foot long by 10-foot wide truck scale, including new approaches and electrical work. The new scale will be located in the same general location as the existing scale. There is no proposed change in operations, hours, etc.
|
JO issued
|
Hyde Park
|
|
Yes
|
05-11-2026
|
|
|
|
JO 7-477
|
JO
|
|
|
82 Route 15
|
Change of retail tenant in existing shopping center from pharmacy to car dealership (the “Project”). Project includes replacement of two signs with signs of the same dimensions, content to be determined. One of the replacement signs will be collocated on an existing freestanding sign along Route 15. The other replacement sign would be mounted on the building above the entrance to the dealership and would be internally illuminated. No other construction is proposed. Up to 50 for-sale vehicles may be stored on site.
|
JO issued
|
Hardwick
|
|
Yes
|
05-11-2026
|
|
|
|
JO 7-478
|
JO
|
|
Jackson Lakeside Realty, LLC;
|
213 Jackson Rd.
|
Request for jurisdictional opinion as to whether converting the ownership of Jackson’s Lodge from a limited liability company to a common interest community requires an Act 250 permit amendment. No physical changes, changes in use or new lot boundaries are proposed.
|
JO issued
|
Canaan
|
|
Yes
|
05-11-2026
|
|
|
|
JO 7-479
|
JO
|
|
|
72 Moose River Dr.
|
a minor reconfiguration of the existing 2-story building to accomodate (5) families and a new common entry, minor HVAC upgrades, and thermal envelope improvements.
|
JO issued
|
Saint Johnsbury
|
|
Yes
|
05-18-2026
|
|
|
|
JO 7-480
|
JO
|
|
|
1222 Main St.
|
Conversion of the 4-story Dean Hale building from commercial office space into a mixed use building containing affordable rental housing.
|
JO issued
|
Saint Johnsbury
|
|
Yes
|
05-25-2026
|
|
|
|
JO 7-481
|
JO
|
|
|
418 Railroad St.
|
Renovation of a 4-Story building that was severely damaged by fire in the summer of 2025.
|
JO issued
|
Saint Johnsbury
|
|
Yes
|
05-25-2026
|
|
|
|
5W0838-6
|
Major
|
Mark Geiger Swenson Granite Company, LLC;
|
Swenson Granite Company, LLC;
|
1127 Cabot Road
|
This permit specifically authorizes the expansion of the quarry’s existing extraction footprint northward. (Extraction will continue from south to north) Operational changes include establishment of a new waste stockpile (grout) storage area on the hillside to the north. A mobile crusher will be brought onsite for a maximum of 45 days per year to process the grout (20,000 cubic yards annually) into a saleable product. Three additional stormwater detention ponds will be constructed downhill of the existing pond. There are no changes proposed to the previously approved 750,000 cubic feet of annual saleable extraction volume.
|
Pending (Hearing)
|
Woodbury
|
06-26-2026
|
No
|
05-18-2026
|
03-17-2026
|
|
|
4A0076
|
Major
|
Town Clerks Office;
|
|
|
Construction of a municipal water supply and distribution system.
|
Withdrawn
|
New Haven
|
|
Yes
|
05-25-2026
|
|
|
|
4A0078-6
|
Minor
|
President & Fellows of Middlebury College;
|
President & Fellows of Middlebury College;
|
63 Château Road
|
Demolition of Battell Hall, a first-year residence dorm on the Middlebury College campus, with associated site improvements and infrastructure modifications. No new construction is proposed or authorized.
|
Permit
|
Middlebury
|
|
Yes
|
05-18-2026
|
04-29-2026
|
|
|
4C0329-16E
|
Minor
|
David Shenk Shenk Properties, LLC;
|
David Shenk Shenk Properties, LLC;
|
55 Thompson Drive
|
This permit specifically authorizes the construction of a 41,250 square foot warehouse building, with 30 employees on an existing 8.65-acre undeveloped parcel; Lot C5B, in the Saxon Hill Industrial Park (the Project). The Project is located at 55 Thompson Drive in Essex, Vermont.
|
Permit
|
Essex, Town of
|
|
Yes
|
05-18-2026
|
05-05-2026
|
|
|
4C0329-21C-1
|
Minor
|
Rob Conboy Glavel, Inc.;
|
Al Senecal Allen Brook Development;
|
131 Red Pine Circle
|
This permit specifically authorizes the extension of the construction timeframe for completing components of the project previously approved under Act 250 Land Use Permit (LUP) 4C0329-21C-1. Construction of the previously approved second bunker, second silo pad and silo was not completed within the original permit’s construction window, and an administrative amendment to extend the deadline was not submitted by the required deadline. This amendment does not propose any changes to the project as previously reviewed and approved.
This amendment does not propose any changes to the project as previously reviewed and approved. All elements remain consistent with the original permit. The sole purpose of this amendment is to allow completion of construction of the already permitted second bunker and second silo pad and silo.
|
Permit
|
Essex, Town of
|
|
Yes
|
05-11-2026
|
01-21-2026
|
|
|
4C0331-44
|
Minor
|
Nicolas Longo City of Burlington c/o Patrick Leahy Burlington International Airport;
|
City of Burlington, Leahy Burlington International Airport;
|
35 Customs Drive
|
This permit specifically authorizes demolition of the 1,800 square foot former carpentry and office building that is currently used for storage. No new structure is planned, and existing utilities will be capped in place (the “Project”). The Project is located at 35 Customs Drive in South Burlington, Vermont.
|
Pending (Comment Period)
|
South Burlington
|
|
No
|
05-25-2026
|
06-16-2026
|
|
|
4C0354-3A
|
Minor
|
GlobalFoundries;
|
GlobalFoundries;
|
1000 River St
|
This permit specifically authorizes the construction of one 53'x32' building to house wastewater treatment equipment to support the on-site treatment of industrial wastewater from site manufacturing operations. The building will be placed within the footprint of the existing permitted wastewater treatment plant. Construction includes excavation for a concrete foundation and piping installation, installation of a prefabricated insulated metal building, and minor demolition of 70’ of walkway and 30’ of curbing to prepare the site. The building will be accessed by a 30’ driveway from the existing roadway. Wastewater treatment equipment, chemical handling equipment, and safety apparatus will be installed in the building. The equipment will be integrated into existing systems and operated by licensed wastewater operators. Stormwater collected by the new impervious surface will be routed to existing infrastructure that collects all stormwater within the waste treatment plant, (the Project).
|
Pending (Comment Period)
|
Essex Junction, City of
|
|
No
|
05-11-2026
|
06-02-2026
|
|
|
4C0608-23C-1
|
Minor
|
Jonathan Lang Why Not, LLC;
|
Jonathan Lang Why Not, LLC;
|
127 Stinson Drive
|
This permit specifically authorizes construction of a 3,600 square foot clubhouse building with a restaurant and pro shop for the Links at Lang Farm Golf Course. The project includes 24 additional parking spaces and a private stormwater treatment system. Water and sewer services will be provided through connections to municipal systems (the “Project”). The Project is located at 127 Stinson Drive in the Town of Essex, Vermont.
|
Pending (Comment Period)
|
Essex, Town of
|
|
No
|
05-18-2026
|
06-09-2026
|
|
|
4C1110-4D
|
Minor
|
The Snyder Williston Properties, LLC;
|
The Snyder Williston Properties, LLC;
|
Alpine Drive & Eden Lane
|
This permit specifically authorizes the construction of the Neighborhood Park in the Annex Residential Neighborhood, as well as the modification of townhome footprint lots 47-52 & 64-76, and the modification of the paved path between Alpine Drive and Eden Lane. The Neighborhood Park includes a swimming pool, amenity building, garden beds, play equipment, and benches.
|
Pending (Comment Period)
|
Williston
|
|
No
|
05-11-2026
|
06-01-2026
|
|
|
2W1320
|
Minor
|
Christina Cullen The 5th Generation Adams Farm, LLC; Christopher Adams 5th Generation Adams Farm, LLC;
|
|
15 Higley Hill Road
|
two paintball courses on 2 1/2 acres, one 6 x 6' storage shed, four forts, approximately 8' x 8' each.
|
Abandoned
|
Wilmington
|
|
Yes
|
05-18-2026
|
|
|
|
1R0337-16
|
Minor
|
Charles Barker GE Aerospace;
|
GE Aerospace;
|
Windcrest Road
|
The project is phase 1 of a two-phase upgrade to the facility’s chemical milling operations. Phase 1 consists of the relocation of existing argon, nitrogen, propane, and hydrogen infrastructure currently located within the footprint of a planned future building expansion (phase 2). No expansion of operations is proposed. All site work will occur within previously developed areas and includes the demolition of two existing outbuildings, removal of associated pavement, construction of new equipment foundations, installation of a prefabricated equipment locker, relocation of underground utilities and piping to reconnect existing operations, and associated drainage improvements to replace and reconnect existing stormwater infrastructure within the work area. Construction will be phased to maintain operations and will include a planned three-day shutdown for final tie-ins, system cutover, and commissioning of relocated infrastructure. No changes to access, traffic patterns, or facility operations are proposed. Phase 2 improvements (building addition and process upgrades) are not proposed.
|
Pending (Comment Period)
|
Rutland Town
|
|
No
|
05-25-2026
|
06-12-2026
|
|
|
1R0669-12
|
Minor
|
Sharron Scott Vermont State Colleges;
|
Sharron Scott Vermont State Colleges;
|
119 Alumni Dr.
|
This permit specifically authorizes the construction of a subsurface infiltration system
and a level spreader with forebay, an underground storage system, and multiple
proprietary filters systems to treat runoff from the existing impervious surfaces at the
property (Vermont State University Castleton Campus) (the “Project”).
The Project is located at 119 Alumni Drive in Castleton, Vermont.
|
Permit
|
Castleton
|
|
Yes
|
05-25-2026
|
05-15-2026
|
|
|
1R0980(Altered)-2
|
Minor
|
Town of Killington;
|
Killington/Pico Ski Resort Partners LLC;
|
Killington Road
|
The project is comprised of the after-the-fact installation of water main distribution pipe for the VWF Water Phase 1 (contract 4) in the existing road prism; and the proposed sequenced, on-alignment, full-depth road reconstruction of Road Phase 1 (section 1A North), an 8-foot wide multi-modal shared use path, stormwater infrastructure to include the replacement of the culverts for the West Branch Roaring Brook and Roaring Brook, construction of a gravel wetland to treat roadway runoff, and the installation of streetlights. No service connections from individual properties to the installed water main are proposed. The Project [segment] is located along Killington Access Road from ~ the Lookout Tavern at 2910 Killington Road to the GMP Snowshed Substation access drive along Killington Road in Killington, Vermont.
|
Pending (Comment Period)
|
Killington
|
|
No
|
05-18-2026
|
06-04-2026
|
|
|
2S1296-1A
|
Minor
|
Glenn Seward Ascutney Outdoors;
|
Glenn Seward Ascutney Outdoors, LLC; Town of West WIndsor Selectboard;
|
449 Ski Road
|
The project is generally described as the installation of two (2) pole lights and proposed after-the-fact authorization for the use of the project tract for non-trail events (in addition to the trail events authorized under Land Use Permit 2S1296-1).
|
Permit
|
West Windsor
|
|
Yes
|
05-18-2026
|
05-06-2026
|
|
|
2W0543-2E
|
Minor
|
171 Route 100 Dover, LLC;
|
171 Route 100 Dover, LLC;
|
171 VT Route 100
|
the construction of a 10' x 20' outdoor seating patio for an existing restaurant and expansion of restaurant seats from 30 to 49 for an increase of 19 seats serving 2 meals per day. This permit also authorizes the as-built expansion of parking area from 17 to 29 spaces for an increase of 12 spaces
|
Pending (Comment Period)
|
Dover
|
|
No
|
05-11-2026
|
06-03-2026
|
|
|
2W0944-5
|
Minor
|
Steve Petrik Southern Vermont Trails Association;
|
Stratton School District;
|
40 Old Town Rd Stratton, VT 05360
|
the construction of approximately 6.45 miles of natural-surface, non-motorized multi-use trails, ADA/ORAR accessibility improvements, and construction of a 50’ x 100’ open-walled timber-framed community events pavilion
|
Pending (Comment Period)
|
Stratton
|
|
No
|
05-11-2026
|
06-04-2026
|
|
|
2W0988-2
|
Minor
|
River Bend Group LLC;
|
Sara Bernard River Bend Group LLC;
|
653 VT Route 30
|
This application includes renovation and addition to an existing commercial building including removal of an existing apartment, removal of an existing food truck/stand and the addition of takeout food (commercial catering) and ice cream to the existing deli/small meat processing and retail store with no public restrooms and no interior restaurant seating to be served by proposed onsite wastewater and water systems.
|
Pending (Comment Period)
|
Townshend
|
|
No
|
05-18-2026
|
06-08-2026
|
|
|
5W0846-14A
|
Minor
|
Irving Oil Retail Sales US LLC;
|
Irving Oil Retail Sales US LLC;
|
159 Paine Turnpike North
|
This permit specifically authorizes the construction of an additional small parking area on the north side of the existing convenience store site at 159 Paine Turnpike North in Berlin to accommodate up to 6 truck spaces. This will include: (1) extending an existing screening berm with additional fence and plantings; (2) the reconfiguration of site lighting to accommodate the new parking area; and (3) the installation of an additional sidewalk to aid in pedestrian circulation along Paine Turnpike (the “Project”).
|
Permit
|
Berlin
|
|
Yes
|
05-25-2026
|
05-06-2026
|
|
|
5W0863-4
|
Minor
|
City of Barre;
|
City of Barre;
|
277 Morrison Road
|
The project is generally described as the redevelopment of the existing O’Reilly Auto Parts warehouse building and site into a public works garage for the City of Barre Department of Public Works (DPW). This would include proposed internal building renovations and reconfiguration of the project site to allow at-grade access to the building by DPW vehicles and to add exterior storage facilities including pipe, material, salt, sand and aggregate storage, and a fueling depot. The project is located at 277 Morrison Road in Barre Town, Vermont.
|
Pending (Hearing)
|
Barre Town
|
|
No
|
05-18-2026
|
|
|
|
5W0758-1A
|
Minor
|
John and Gretchen King;
|
John and Gretchen King;
|
653 Perry Lea Rd
|
This permit specifically authorizes the installation of a new swimming pool and fire pit patio, reconstruction of the existing deck, an 8’ x 8’ pool equipment shed, and interior renovation of the existing residence to add a fourth bedroom and dormer. The wastewater system will be upgraded to accommodate an additional bedroom and will be designed with capacity for future expansion not authorized by this permit (the “Project”). The Project is located at 653 Perry Lea Rd in Waterbury, Vermont.
|
Permit
|
Waterbury
|
|
Yes
|
05-18-2026
|
05-06-2026
|
|
|
5L0877-8
|
Minor
|
Town of Morristown;
|
Town of Morristown;
|
Jersey Way, Foss Street
|
This permit specifically authorizes the installation of a gravel wetland pond stormwater conveyance features to treat stormwater runoff from impervious surfaces associated with the Jersey Heights Subdivision to meet VT ANR 3-9050 General Stormwater permit requirements as a 3-acre site. The proposed gravel wetland is located on the "common land" of the subdivision, which has recently been conveyed to the Town of Morristown. Drainage conveyance features including stormwater structures, piping, and swales will be installed in the Town roadway right-of-way as well as on private land under easement to the Town. (the “Project”). The Project is located at Jersey Way and Foss Street in Morristown, Vermont.
|
Pending (Comment Period)
|
Morristown
|
|
No
|
05-18-2026
|
06-10-2026
|
|
|
5L1085-3
|
Minor
|
Stowe Land Trust;
|
Stowe Land Trust;
|
2993 Stagecoach Road
|
The reconfiguration of the boundaries of two parcels of land through concurrent subdivision and merger to create parcel 12062 to be comprised of 5.53 acres with an existing single-family residence to be made available for additional future development. Parcel 12062-3, to be comprised of 31.82 acres will be put into conservation. No change in use or physical disturbance is proposed as part of the project.
|
Pending (Comment Period)
|
Morristown
|
|
No
|
05-25-2026
|
06-16-2026
|
|
|
5R1631
|
Minor
|
Laurence Hebert Hebert Housing;
|
Hebert Housing LLC;
|
2511 VT Route 14
|
This permit applies to the lands identified in Book 184, Pages 557-558 of the land records of Williamstown, Vermont as the subject of a deed to Hebert Housing LLC. This permit specifically authorizes the construction of two, four unit, 2- bedroom apartment buildings with sixteen parking spaces (two spaces per unit). One of the units will be fully ADA compliant. All other on grade units will meet Vermont Access Rules for adaptability. All second-floor apartments will be visitable. The project will be served by connections to municipal water and septic systems. The .30 acres project tract is located at 2511 VT Route 14 in Williamstown, Vermont
|
Pending (Comment Period)
|
Williamstown
|
|
No
|
05-11-2026
|
06-01-2026
|
|
|
4C1224-7
|
Minor
|
Mactaw VT Realty, LLC;
|
Mactaw VT Realty, LLC;
|
400 Route 7 South
|
This permit specifically authorizes the placement of 5-feet of clean fill on a footprint of 120-feet x 360-feet with temporary access on Lot 4 of the existing subdivision (total/maximum fill volume will be approximately 5,5000 cubic yards) (the “Project”). The fill area was previously authorized for “temporary grass RV storage area” under Land Use Permit 4C1224-7.
The Project is located at 400 Route 7 South in Milton, Vermont.
|
Permit
|
Milton
|
|
Yes
|
05-25-2026
|
05-05-2026
|
|
|
4C1350-1
|
Minor
|
Todd Odit Town of Hinesburg;
|
Town of Hinesburg;
|
10004 Rte 116
|
This permit specifically authorizes Hinesburg Well #6 to be placed into service to supplement the Town of Hinesburg's (the Town) existing water source capacity and improve system reliability. Well #6 was previously drilled and permitted, but has not yet been equipped with a pump, controls, electrical equipment, or physically connected to the Town's water system. There is no increase in the permitted capacity of the water system. Construction includes a new submersible well pump and associated accessories, new electrical service, new variable frequency drive, controls, and radio telemetry at both Well #6 and the water treatment facility, and a new 8' x 10' electrical control building adjacent to Well #6.
|
Pending (Comment Period)
|
Hinesburg
|
|
No
|
05-11-2026
|
05-25-2026
|
|
|
4C1366-1
|
Minor
|
Town of Shelburne;
|
Dubrul Family LLC (Automaster); Town of Shelburne;
|
113 Crown Road
|
This permit specifically authorizes the Town of Shelburne - Wastewater Treatment Facilities Consolidation, Contract No.2. The project will focus on decommissioning wastewater treatment facility (WWTF) #2, located on 53 Turtle Lane, and upgrading WWTF #1, located on 113 Crown Road. WWTF #2 has an area of 50.88 acres. WWTF #1 has an area of 4.3 acres; a property boundary line adjustment will occur on the north side of WWTF #1 with a property owned by Dubrul Family LLC (Automaster), subject to Act 250 permit series 4C1053. The consolidation of the two facilities involves converting WWTF #2 to a pump station. External work includes the demolition and construction of structures and various internal work, (the “Project”).
|
Pending (Comment Period)
|
Shelburne
|
|
No
|
05-11-2026
|
05-26-2026
|
|
|
500049-4
|
Minor
|
City of Barre;
|
City of Barre;
|
69 Treatment Plant Drive
|
The project involves the demolition of the existing headworks building to be replaced by the construction of a new 2,000 square foot metal headworks building, installation of related yard piping, and demolition of an existing unused ice rink and storage building. The building will be floodproofed to the 500-year flood elevation. The project is located at 69 Treatment Plant Drive in Barre City, Vermont
|
Pending (Comment Period)
|
Barre City
|
|
No
|
05-11-2026
|
06-01-2026
|
|
|
5L0642-10
|
Minor
|
ACABAY, INC; Jeffrey & Porter C.N Sutton-Shebab;
|
ACABAY, INC.; Jeffrey & Porter C.N Sutton-Shebab;
|
Weeks Hill Meadows
|
This permit specifically authorizes a boundary line adjustment of the ACABAY, INC. parcel from 41.0 acres to 40.3 acres. The receiving Shehab & Sutton-Shehab Parcel will increase from 0.13 acres to 0.85 acres (the “Project”). The Project is located at 15 Weeks Hill Meadows in Stowe, Vermont.
|
Pending (Comment Period)
|
Stowe
|
|
No
|
05-18-2026
|
06-03-2026
|
|
|
5L0679-5
|
Minor
|
Dennis Hill Wolcott School District;
|
Dennis Hill Wolcott School District;
|
320 School Hill Drive
|
This permit specifically authorizes the construction of an in-ground village wastewater disposal system for the Town of Wolcott, which will be constructed in the existing open fields to the southwest of the school building. The 50,000 square feet disposal fields will consist of a drip disposal system with small diameter pipes buried one foot below grade. Septic tank effluent will be pumped to the disposal fields from the control building and settling tanks. Construction involves the installation of one buried 1,500 gallon settling tank, two buried 10,000-gallon equalization tanks, a 12'x14' control building, and associated piping infrastructure. The 24.66 acres tract is located at 320 School Hill Drive in Wolcott.
|
Pending (Comment Period)
|
Wolcott
|
|
No
|
05-11-2026
|
06-02-2026
|
|
|
5L0708-13
|
Minor
|
133 Gallery Lane LLC;
|
133 Gallery Lane LLC;
|
105 Gallery Lane
|
This permit amendment applies to the lands identified in Book 318, Page 164 of the land records of the Morristown, Vermont as the subject of a deed to 133 Gallery Lane LLC. This permit specifically authorizes a change of use (no external construction) for the commercial structure located on Lot B at 105 Gallery Lane in Morristown. The former mattress warehouse tenant has vacated, and the new tenant will establish an exercise/gym facility in the majority of the building (Unit 1) while Unit 2, now vacant, will be offered as potential retail space.
|
Pending (Comment Period)
|
Morristown
|
|
No
|
05-18-2026
|
06-09-2026
|
|
|
8B0624-1
|
Minor
|
Jessica Rhys;
|
Jessica Rhys; Timothy Rhys;
|
106 Palmer Place
|
This permit specifically authorizes the Conversion of a portion of an existing residence (Rice House) to a daycare, reduction of the number of bedrooms in the Rice House from three to two, and conversion of a separate building (called the Wheelwright Shop) to a bookstore (the “Project”). The Project is located at 106 Palmer Place in Manchester, Vermont.
|
Permit
|
Manchester
|
|
Yes
|
05-18-2026
|
04-17-2026
|
|
|
9A0246
|
Minor
|
Rene & Lorraine Quenneville;
|
|
|
Storage garage
|
Withdrawn
|
Leicester
|
|
Yes
|
05-25-2026
|
|
|
|
9A0312-4
|
Minor
|
Don Maglienti Addison County Solid Waste Management District;
|
Addison County Solid Waste Management District;
|
145 Campground Road
|
(1) Construction of a ±310 square foot attendant building within “Phase 2” of the existing ACSWMD transfer station facility upon Lot 6 of the Norris Subdivision; and (2) expansion of existing ACSWMD operations onto an adjacent ±2.0-acre lot. The expansion aspect of the project includes demolition of an existing structure on the “Church Lot” and construction of a new ±3,250 square foot Household Hazardous Waste (HHW) facility with associated access drive, parking, and stormwater improvements. The project will be served by an on-site drilled well and an existing community mound wastewater disposal system.
|
Permit
|
New Haven
|
|
Yes
|
05-18-2026
|
05-13-2026
|
|
|
5W1595-2
|
Minor
|
Cross Vermont Trail Association;
|
Cross Vermont Trail Association;
|
Between Gallison Hill Road Montpelier and Rte 14 in E. Montpelier
|
Trails to provide an off road non motorized alternative to Rte 2 and Rte 14 as well as recreation access to natural areas. This project involves construction or improvement of a total of 1.13 miles of trail (0.79 miles new path separate from roads and 0.34 miles colocated with existing private farm road.) New trail will be a simple gravel path 3 - 5 feet wide. There will also be installation along the trail of signs for wayfinding and for interpretation of natural and cultural heritage. This is the final phase of the larger Cross Vermont Trail project between Gallison Hill Road in Montpelier and Rte 14 in East Montpelier. This application is intended to amend existing project permit #5W1595 by adding to it this final phase and by extending the construction deadline for the permitted project.
|
Pending (Comment Period)
|
East Montpelier
|
|
No
|
05-25-2026
|
06-09-2026
|
|
|
700002-19C-F
|
Minor
|
Aaron Sherritt Hermitage Members Club, Inc.;
|
Aaron Sherritt Hermitage Members Club, Inc.; Josh DeBottis Hermitage Members Club, Inc.;
|
10 Gatehouse Road
|
the construction of a new ski patrol building.
|
Permit
|
Wilmington
|
|
Yes
|
05-11-2026
|
04-01-2026
|
|
|
700002-32-1
|
Minor
|
MBSA Development Company, LLC;
|
MBSA Development Company, LLC;
|
Gatehouse Trail & Old Mill Crossing
|
the construction of the sewer line, water line, and electric line serving Lot 1; electric line serving Lots 2-5; clearing of Lot 1 house location; stumping and grading of Lot 1-5 house locations; and construction of the 5-bedroom Lot 5 house and associated permeable pavement
|
Permit
|
Wilmington
|
|
Yes
|
05-18-2026
|
05-06-2026
|
|
|
700002-33
|
Minor
|
Aaron Sherritt Hermitage Members Club. Inc.;
|
Aaron Sherritt Hermitage Members Club. Inc.; Josh DeBottis Hermitage Members Club. Inc.;
|
10 Gatehouse Road
|
the installation of a new ski lift at Hermitage Members Club along approximately the same alignment as the former lift, extending from the base lodge snow front to the mid-mountain cabin along the Needle and Hayfever ski trails. Construction includes: new foundations, towers, chair barn, and top and bottom terminals with supporting grading and drainage improvements near the terminal areas, and selective tree cutting (as necessary) for proposed grading at the top terminal
|
Pending (Comment Period)
|
Wilmington
|
|
No
|
05-11-2026
|
06-03-2026
|
|
|
7C0024-4-1
|
Minor
|
New Leaf Realty, LLC;
|
New Leaf Realty, LLC;
|
143 VT 15 West
|
(a) a 2,168-square-foot building addition, (b) new canopy along the western building face, (c) re-grading and paving a portion of the existing gravel parking area, (d) installation of stormwater treatment practices, (e) installation of one new building-mounted exterior light, and (f) replacement of exterior light fixtures in the existing canopy.
|
Permit
|
Hardwick
|
|
Yes
|
05-18-2026
|
02-05-2026
|
|
|
7C0600-12-2
|
Minor
|
Adrienne W.S. Wheeler;
|
Adrienne W.S. Wheeler; Richard R. Wheeler; Sean Dowd Heaven's Bench, LLC;
|
Darling Hill Road
|
To construct a single family dwelling with on-site sewer and water systems on 4 acre rural residential lot. There will be a house with an attached garage and a 10 x 14 shed.
|
Permit
|
Lyndon
|
|
Yes
|
05-25-2026
|
05-11-2026
|
|
|
8B0268-18
|
Minor
|
Dorset Field Club, Inc.;
|
Dorset Field Club, Inc.;
|
102 Parsons Lane
|
This permit specifically authorizes the establishment of a croquet court/event space and construction of additional parking (24 spaces) (the “Project”).
The Project is located at 86 and 102 Parsons Lane in Dorset, Vermont.
|
Permit
|
Dorset
|
|
Yes
|
05-25-2026
|
05-19-2026
|
|
|
8B0527-2
|
Minor
|
John Tietgens, Jr.;
|
Heather Tietgens; John Tietgens, Jr.;
|
89 Main Road
|
The proposed restoration of wetlands and ponds; reduction of impervious surface; and after-the-fact relocation of driving range attendant building and tees/golf features from what was approved in 8B0527 and -1; installation of an ~0.4-acre horse riding arena; a 40-foot by 60-foot storage/maintenance garage along with an accessory outbuilding, trailers, and a dumpster [all for non-commercial use]; a driveway serving the storage garage [and previously approved solar panel array]; a parking area adjacent to the storage garage; and remediation of a staging area for tailings and millings north of the driveway (the “Project”). No other improvements or uses are proposed
|
Pending (Comment Period)
|
Stamford
|
|
No
|
05-11-2026
|
05-29-2026
|