Skip Navigation LinksHome > Projects List > Phase 2 > Data Entry

Upper Otter Creek

Return to Segment List   Step 0Step 1Step 2Step 3Step 4Step 5Step 6Step 7QA CheckMap


Record: 18    Segment ID: M30-    Stream Name: Upper Otter Creek

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

Channel Bed and Planform Changes  
5.1 Bar Types  
  Mid Bar 0
  Point Bar 0
  Side Bar 0
  Diagonal Bar 0
  Delta Bar 1
  Island Bar 2
5.2 Migration Features  
  Flood Chutes 4
  Neck Cutoffs 0
  Channel Avulsions 0
  Braiding 1
5.3 Steep Riffles and Head Cuts  
  Steep Riffles 0
  Head Cuts 0
  Tributary Rejuvenation No
5.4 Stream Ford or Animal Crossing No
5.5 Channel Alterations  
  Straightening Straightening
  Straightening Length 697 ft.
  Dredging None

Comments:
A C4 channel through a narrow and semi-confined valley with a natural bedrock grade control section in the middle. Bank armoring and straightening have impacted much of the reach. The reach begins to look like an E channel as the slope flattens near the end of the reach and the valley walls widen. Note: Unconsolidated silt in bed and banks.