Record: 17    Segment ID: M14-    Stream Name: Tyler Branch

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

Valley and Floodplain Corridor
1.1 Segmentation Planform and Scope  
  Comments also lack of grade control relative to upstream  
1.2 Alluvial Fan None  
1.3 River Corridor Encroachments
  One Side (New) Both Sides (New) Average Height
  Berm Length 0 ft. 0 ft. 0.0 ft.
  Road Length 27 ft. 0 ft. RH1=0.0 ft.
  Railroad Length 0 ft. 0 ft. 0.0 ft.
  Improved Path Length 0 ft. 0 ft. 0.0 ft.
  Development Length 0 ft. 0 ft.  
1.4 Adjacent Terrace or Hillside
  Left Corridor Right Corridor  
  Slope Very Steep Steep  
  Continuous with Bank? Sometimes Sometimes  
  Within 1 Bankfull Width? Sometimes Sometimes  
  Texture Mixed Mixed  
1.5 Valley Features
  Valley Width 280 ft.  
  Valley Width Determination Measured  
  Confinement Type BD  
  Segment in a rock gorge? No  
  Human-caused change
in valley width?
No  
1.6 Grade Controls No Data