ReachPhaseImpactSub ImpactLocationLength (ft.)Name 1Value 1Name 2Value 2
R16.S2.03-S1.01-A2Bank Armoring or RevetmentRip-RapLeft Bank34.19035Length34 0
R16.S2.03-S1.01-A2Bank Armoring or RevetmentRip-RapLeft Bank273.3372Length273 0
R16.S2.03-S1.01-A2Bank Armoring or RevetmentRip-RapRight Bank24.75846Length25 0
R16.S2.03-S1.01-A2Bank Armoring or RevetmentRip-RapRight Bank63.28737Length63 0
R16.S2.03-S1.01-A2Bank Armoring or RevetmentRip-RapRight Bank171.5426Length172 0
R16.S2.03-S1.01-A2Bridge or CulvertCulvert 0Length41 0
R16.S2.03-S1.01-A2Buffers Less than 25 feet Left Bank265.903Length266 0
R16.S2.03-S1.01-A2Buffers Less than 25 feet Right Bank831.8753Length876 0
R16.S2.03-S1.01-A2EncroachmentRoadOne Side224.214 0Length224
R16.S2.03-S1.01-A2Erosion Left Bank31.17696Height4Length31
R16.S2.03-S1.01-A2Erosion Left Bank66.56181Height3Length67
R16.S2.03-S1.01-A2Erosion Right Bank39.22282Height3Length39
R16.S2.03-S1.01-A2Erosion Right Bank132.0346Height4Length132
R16.S2.03-S1.01-A2Stormwater InputOverland Flow 0 0 0
R16.S2.03-S1.01-A2StraighteningStraightening 831.8753Length882 0