Return to Reach List   Step1Step2Step3Step4Step5Step6Step7Map


Record: 24    Reach ID: T2.11    Stream Name: Water Andric

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

    Data values Metadata
7.1 Bank Erosion/Height   Project Default
  Erosion Length 430.5400085  
  Height 6.624  
  (old) Bank Erosion None  
  (old) Bank Height No Data  
  Impact Low  
7.2 Ice/Debris Jam Potential Debris Field obs. along entire reach
  Impact High  
7.3 Comments T2.11 was segmented during Phase 2 assessments. Segment A is 3,714 feet and is a C3 riffle-pool. A large alluvial fan was observed at the top of Segment A, the slope increases above the fan and Segment B is B3 step-pool sub-reach and is 3,500 feet long. Numerous debris jams were observed throughout the reach during Ph2 assessment. Most debris jams were associated with mass failures and bends in the channel.