5.1 Flow Regulation   Project Default
  Flow Regulation Type None  
  Flow Regulation Use  
  (Old) Flow Regulation  
  Impact Not Significant  
5.2 Bridges & Culverts Project Default
  Number 2  
  Reach Length / Percent 23 ft. 0.5 %  
  Impact Not Significant  
5.3 Bank Armoring Project Default
  Left Right  
  Length 305 ft. 874 ft.  
  Percent 24.4 %  
  Length (old) %  
  Impact High  
5.4 Channel Straightening Project Default
  Length / Percent 2,042 ft. 42.3 %  
  Impact High  
5.5 Dredging History None Project Default
  Impact Not Significant