Skip Navigation LinksHome > Projects List > Phase 1 > Data Entry

Upper Otter Creek

Return to Reach List   Step1Step2Step3Step4Step5Step6Step7Map


Record: 9    Reach ID: M21    Stream Name: Upper Otter Creek

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

  Data values Metadata
5.1 Flow Regulation   Project Default
  Flow Regulation Type Small Run of River  
  Flow Regulation Use Other  
  (Old) Flow Regulation Bypass  
  Impact Low  
5.2 Bridges & Culverts Project Default
  Number 4  
  Reach Length / Percent 1,700 ft. 23.5 %  
  Impact High  
5.3 Bank Armoring Project Default
  Left Right  
  Length 1,794 ft. 2,908 ft.  
  Percent 64.9 %  
  Length (old) %  
  Impact High  
5.4 Channel Straightening Project Default
  Length / Percent 7,222 ft. 99.6 %  
  Impact High  
5.5 Dredging History None Project Default
  Impact Not Significant