Skip Navigation LinksHome > Projects List > Phase 1 > Data Entry

Winooski Mid, Alder to Montp

Return to Reach List   Step1Step2Step3Step4Step5Step6Step7Map


Record: 79    Reach ID: R13.S1.02-S1.02-S1.01    Stream Name: Unnamed Tributary

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

  Data values Metadata
5.1 Flow Regulation   Project Default
  Flow Regulation Type None  
  Flow Regulation Use  
  (Old) Flow Regulation  
  Impact Not Significant  
5.2 Bridges & Culverts Project Default
  Number 5  
  Reach Length / Percent 240 ft. 2.5 %  
  Impact Not Significant  
5.3 Bank Armoring Project Default
  Left Right  
  Length 330 ft. 176 ft.  
  Percent 5.3 %  
  Length (old) %  
  Impact Low  
5.4 Channel Straightening Project Default
  Length / Percent 2,531 ft. 26.3 %  
  Impact High  
5.5 Dredging History Dredging Project Default
  Impact High