Skip Navigation LinksHome > Projects List > Phase 1 > Data Entry

Clyde

Return to Reach List   Step1Step2Step3Step4Step5Step6Step7Map


Record: 1    Reach ID: M01    Stream Name: Clyde River

Go to First  Go to Prev  Go to Next  Go to Last  ChangeLog

Data values Metadata
4.1 Watershed Land Cover   Project Default
  Historic Project Default
  Current Dominant Forest 72.0 %  
  Current Sub-Dominant Crop 6.0 %  
  Urban 5.0 %  
  Crop 6.0 %  
  Impact High  
4.2 Corridor Land Cover   Project Default
  Historic Project Default
  Current Dominant Crop 19.0 ft.  
  Current Sub-Dominant Field 18.0 ft.  
  Urban 18.0 %  
  Crop 19.0 %  
  Impact High  
4.3 Riparian Buffer Width   Project Default
  Left Right  
  Dominant 0-25 >100
  Sub-dominant 26-50 0-25
  Length where less than 25 Feet 4,388 3,002 ft.
  Impact High  
4.4 Groundwater Inputs None Project Default