Newly Reported Overflow
|
|
|
Facility Name:
|
|
|
Facility Number:
|
|
|
PermitID:
|
|
|
Submission Number:
|
HQQ-8PDJ-06R3J
|
|
Current Status:
|
Submitted
|
|
SubVersionID:
|
dd550b45-50a2-4905-be24-f987f005a51c
|
|
Location:
|
120 Lesle Drive White River Junction, VT 05001
|
|
Caller Name And Title:
|
Max Tier Chief of Wastewater
|
|
Incident Start Date:
|
07/17/2026
|
|
Incident End Date:
|
07/22/2026
|
|
Contact Name And Title For Public:
|
Max Tier
|
|
Public Contact Phone Number:
|
1-603-443-3839
|
|
Incident Start Time:
|
01:00 pm
|
|
Incident End Time:
|
01:00 pm
|
|
Estimated Volume:
|
50
|
|
Nature Of Incident:
|
Discharged untreated sewage
|
|
Cause Of Discharge:
|
Mechanical Failure
|
|
Type Of Obstruction:
|
Air release valve fail
|
|
Point Of Discharge:
|
Manhole
|
|
Corrective Action Taken:
|
Notified Brett Mayfield, Health Inspector for town of Hartford. Posted signs along wetland on park side. Emergency pump truck on site with highway traffic control and police officer. Began researching potential fails with town engineer. Started process of locating new valve and shut off. Scheduled pump truck every two days with Stearns. Vactor truck to clean and remove existing failed valve. by-pass until new valve arrives. Estimated outfall is less than 50 gallons as majority of sewage contained in pump station and valve pit. 7/23/2026 Operator is adding additional signage to notify public.
|
|
Waterbody Impacted:
|
wetland
|
|
Description Of Incident:
|
The air release valve on forced main has failed. Need to replace. valve pit spurts sewage from valve when pumps engage.
|