Newly Reported Overflow
|
|
|
Facility Name:
|
|
|
Facility Number:
|
|
|
PermitID:
|
|
|
Submission Number:
|
HQJ-FNHY-85G8C
|
|
Current Status:
|
In Review
|
|
SubVersionID:
|
84aaec7e-0dad-4a0b-bafa-11756cf2afe0
|
|
Location:
|
WWTF outfall
|
|
Caller Name And Title:
|
Nick Geneva - Chief of Wastewater
|
|
Incident Start Date:
|
01/08/2026
|
|
Incident End Date:
|
|
|
Contact Name And Title For Public:
|
Nick Geneva
|
|
Public Contact Phone Number:
|
8022362623
|
|
Incident Start Time:
|
08:30 am
|
|
Incident End Time:
|
|
|
Estimated Volume:
|
300000
|
|
Nature Of Incident:
|
Discharged treated and partially disinfected effluent
|
|
Cause Of Discharge:
|
Other - Please describe in Description of Incident
|
|
Type Of Obstruction:
|
|
|
Point Of Discharge:
|
WWTF outfall
|
|
Corrective Action Taken:
|
Bulbs have been replaced and u.v banks have been cleaned and disinfected. The weir after disinfection (before sample point) has been drained, cleaned and disinfected multiple times. Today I received new butterfly valves for the bank that was not in service and replaced them so that eliminates the possibility of anything leaking by when the bulbs aren't on.
|
|
Waterbody Impacted:
|
Otter Creek
|
|
Description Of Incident:
|
We have contamination in our U.V system from 2 failing butterfly valves that raw effluent was leaking through on the secondary u.v bank that was not in operation.
|