Vermont Watershed Management in DEC at ANR


Newly Reported Overflow
Facility Name:
Facility Number:
PermitID:
Submission Number: HNP-4ZCY-739R3
Current Status: Deemed Complete
SubVersionID: 74618fb7-be21-4a67-9e45-20a6da4a8163
Location: CSO 003 -Bailey Ave
Caller Name And Title: Christopher Cox - Chief Operator
Incident Start Date: 4/19/2019
Incident End Date: 4/19/2019
Contact Name And Title For Public: Kurt Motyka
Public Contact Phone Number: 802-223-9508
Incident Start Time: 08:00 am
Incident End Time: 03:00 pm
Estimated Volume: Under 100 gallons
Nature Of Incident: Authorized Wet Weather CSO Overflow
Cause Of Discharge: High Flows
Type Of Obstruction: None
Point Of Discharge: Combined sewer overflow structure
Corrective Action Taken: None.
Waterbody Impacted: Winooski River
Description Of Incident: High flows caused by snow melt resulted in the discharge of a combination of sewage and stormwater from CSO 003 - Bailey Ave. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.