Vermont Watershed Management in DEC at ANR


Newly Reported Overflow
Facility Name:
Facility Number:
PermitID:
Submission Number: HNF-JHC6-ZN934
Current Status: Deemed Complete
SubVersionID: 817ad6eb-ea07-411e-ba18-d87d30a69b1e
Location: Third Base: Meadow Street CSO#003 and School Street CSO#004
Caller Name And Title: Rod Munroe/ Lab Director
Incident Start Date: 7/25/2018
Incident End Date: 7/25/2018
Contact Name And Title For Public: Jeff Wennberg, Commissioner of Public Works, City of Rutland
Public Contact Phone Number: 802-773-1813
Incident Start Time: 10:50 am
Incident End Time: 01:16 pm
Estimated Volume: 70,043 gallons
Nature Of Incident: Authorized Wet Weather CSO Overflow
Cause Of Discharge: High Flows
Type Of Obstruction: None
Point Of Discharge: Combined sewer overflow structure
Corrective Action Taken: none
Waterbody Impacted: East Creek
Description Of Incident: High flows caused by an intense rain storm on 07/25/18 resulted in the discharge of a combination of sewage and stormwater from CSO#009- School and Meadow Street combined, CSO#003 and #004. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings. In addition, 2,919,042 gallons of urban storm water was treated through the wastewater treatment plant that would have otherwise gone into the receiving stream.