Newly Reported Overflow
|
|
|
Facility Name:
|
|
|
Facility Number:
|
|
|
PermitID:
|
|
|
Submission Number:
|
HN7-1TF5-C17BK
|
|
Current Status:
|
Deemed Complete
|
|
SubVersionID:
|
0f265ddc-8574-4c2d-874b-f58ebdf5747f
|
|
Location:
|
Macdonough Drive Pump Station
|
|
Caller Name And Title:
|
Rick Chaput, Chief Operator
|
|
Incident Start Date:
|
08/12/2017
|
|
Incident End Date:
|
08/12/2017
|
|
Contact Name And Title For Public:
|
Rick Chaput, Chief Operator
|
|
Public Contact Phone Number:
|
(802) 877-2931
|
|
Incident Start Time:
|
06:30 pm
|
|
Incident End Time:
|
10:00 pm
|
|
Estimated Volume:
|
111,700
|
|
Nature Of Incident:
|
Authorized Wet Weather CSO Overflow
|
|
Cause Of Discharge:
|
High Flows
|
|
Type Of Obstruction:
|
NA
|
|
Point Of Discharge:
|
Pump station emergency overflow pipe
|
|
Corrective Action Taken:
|
None
|
|
Waterbody Impacted:
|
Otter Creek below the falls in Vergennes
|
|
Description Of Incident:
|
High flows caused by an intense rain storm on August 12 2017 resulted in the discharge of a combination of sewage and stormwater from CSO 001. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|