Newly Reported Overflow
|
|
Facility Name:
|
|
Facility Number:
|
|
PermitID:
|
|
Submission Number:
|
2JG-J63N-6P4C
|
Current Status:
|
Deemed Complete
|
SubVersionID:
|
be756c68-8101-411a-8aa6-aa333631fe73
|
Location:
|
Pine Street Burlington VT
|
Caller Name And Title:
|
Tim Grover, Chief Operator
|
Incident Start Date:
|
09/11/2016
|
Incident End Date:
|
09/11/2016
|
Contact Name And Title For Public:
|
Megan Moir, Water Resources Director
|
Public Contact Phone Number:
|
802-863-4501
|
Incident Start Time:
|
05:30 am
|
Incident End Time:
|
05:56 am
|
Estimated Volume:
|
1,000 to 10,000 gallons
|
Nature Of Incident:
|
Discharged untreated sewage
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
None
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
Some upstream catch basins have been disconnected from the combined sewer system. The City is developing a long term plan to eliminate the CSO.
|
Waterbody Impacted:
|
Pine Street Barge Canal
|
Description Of Incident:
|
High flows caused by an intense rain storm on 9/11/16 resulted in the discharge of a combination of sewage and stormwater from the CSO located on Pine Street.This CSO is intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and buildings.
|