Facility Name:
|
Montpelier
|
Caller Name And Title:
|
Christopher Cox - Chief Operator
|
Municipality:
|
City of Montpelier
|
Location (street or site):
|
949 Dog River Road Montpelier, VT
|
Incident Start Date:
|
03/22/2021
|
Incident End Date:
|
03/24/2021
|
Incident Start End Times:
|
08:30 am to 06:20 am
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Discharged treated and partly disinfected effluent
|
Estimated Volume (gallons):
|
>1,000,000 gallons
|
Cause Of Discharge:
|
Unknown
|
Type Of Obstruction:
|
None
|
Point Of Discharge:
|
WWTF outfall
|
Corrective Action Taken:
|
Inspected all UV Banks (ballast cards and lamps). Resolve identified electrical issue. Resample final effluent.
|
Waterbody Impacted:
|
Winooski River
|
Contact Name And Title For Public:
|
Kurt Motyka - Deputy Public Works Director
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
On 3/22/21 final effluent failed E.Coli test (400 C.F.U).
On 3/24/21 final effluent passed E.Coli test (27 C.F.U)
|
|
|
nForm Submission Number:
|
HP7-E49F-9N5ZK
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|