Facility Name:
|
Newport City
|
|
|
Jason Herman Chief Operator
|
|
|
Newport City
|
|
|
1057 Coventry St
|
|
|
05/08/2023
|
|
|
05/10/2023
|
|
|
06:00 pm to 01:30 pm
|
|
|
|
|
|
Other
|
|
|
Under 100 gallons
|
|
|
Mechanical Failure
|
|
|
|
|
|
No discharge to surface water
|
|
|
Dry and wet well pit were pumped down and hauled to our WWTF. Hole in basin was plugged, and pumps are being rebuilt. We will be pumping out any sewage and hauling it to our WWTF until the new pumps are in service
|
|
|
Lake Memphremagog
|
|
|
Jason Herman Chief Operator
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Coventry pump station failed, due to a broken bolt on a pump. Pump station was flooded. There was no sewage released onto the ground, but it is believed sewage was discharged into the ground through a leak in the wet well basin.
Update: Upon further investigation and excavation, it appears the sewage was contained within the wet well/dry pit and distribution system. There was no visual sign of sewage in the ground. There was no leak through the wall of the wet well as we initially thought.
|
|
|
|
|
|