View FacilityIncident Record


Facility Name: Lunenburg FD2    
Rodger Sheldon Chief Operator    
Lunenburg FD #2    
Pump Station    
10/14/2026    
10/14/2026    
05:00 am to 08:00 am    
   
Discharged untreated sewage    
1000    
Mechanical Failure    
   
Pump station emergency overflow pipe    
Parts ordered and should be onsite 10/15. Controls tech to be on site 10/15 to diagnose why lag pump did not start. Report to be left open until repairs are made but at this point station is operating on 1 pump. Notified at 4:00 PM 10/15/2026 that repairs have been made and both pumps are working as designed.    
Connecticut River    
Rodger Sheldon Chief Operator    
   
   
nForms    
Y    
   
   
   
Lead pump failed due to vacuum hose defect. Lag pump failed to start. Lag pump is running and parts ordered to repair pump 1.    
   
HQS-9XY7-JSKEJ