Facility Name:
|
Fair Haven
|
|
|
Carrie LaFond Chief Operator
|
|
|
Town of Fair Haven
|
|
|
Waste Water Treatment Facility
|
|
|
09/01/2021
|
|
|
09/02/2021
|
|
|
08:00 pm to 05:00 am
|
|
|
|
|
|
Discharged partly treated undisinfected effluent
|
|
|
Other
|
|
|
Power Outage
|
|
|
unknown
|
|
|
WWTF outfall
|
|
|
Breaker was reset and being replaced. New back will be implemented and construction workers have been advised to not use power in the building.
|
|
|
Castleton River
|
|
|
Joesph Gunther
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
The waste water facility is currently under construction and a possible overload on the panel occurred causing the breaker to fail.
|
|
|
|
|
|
HPB-E1W9-W69F4
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|