Facility Name:
|
Fair Haven
|
|
|
Peter Laramie, Chief Operator
|
|
|
Fair Haven
|
|
|
Adams Street Pump Station
|
|
|
04/15/2019
|
|
|
04/16/2019
|
|
|
01:58 pm to 03:30 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>10,000 to 100,000 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Pump station emergency overflow pipe
|
|
|
None
|
|
|
Castleton River
|
|
|
Peter Laramie
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on April 15, 2019 resulted in the discharge of a combination of sewage and stormwater from CSO-001 at Adams Street. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HNP-1ZVE-43MJ9
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|