Facility Name:
|
Fair Haven
|
|
|
Pete Laramie, Cheif Operator
|
|
|
Fair Haven
|
|
|
WWTF
|
|
|
04/07/2016
|
|
|
04/08/2016
|
|
|
5:00 pm to 7:00 am
|
|
|
Max of 14 hours
|
|
|
Discharged treated and undisinfected effluent
|
|
|
100,000
|
|
|
Chem Feed Problem
|
|
|
|
|
|
WWTF Outfall
|
|
|
The power inverter for the chlorine feed pump failed, so there was no power gettgin to the pump. This happened sometime after the operators left on Thur afternoon. It was found early the next morning and fixed by 7:00 am.
|
|
|
Castleton River
|
|
|
Pete Laramie, Cheif Operator
|
|
|
04/08/2016
|
|
|
David DiDomenico
|
|
|
Phone
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
The power inverter for the chlorine feed pump failed, so there was no power gettgin to the pump. This happened sometime after the operators left on Thur afternoon. It was found early the next morning and fixed by 7:00 am.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|