Facility Name: Chelsea    
Michael Whipple    
Town of Chelsea    
234 VT Route 110 behind waste water treatment facility    
07/05/2023    
07/05/2023    
10:45 am to 11:45 am    
   
Discharged treated and partly disinfected effluent    
Other    
High Flows    
spike in flow do to weekly wasting proce    
WWTF outfall    
We will increase the Total Residual Chlorine during the wasting periods. We will also take measures to reduce the spike in flow by monitoring the flow while recovering after pumping waste sludge is complete. Bringing the flow back to normal conditions as slowly as possible.    
first branch of the white rivier    
Geoff Clayton Town of Chelsea Health officer    
   
   
nForms    
Y    
   
   
   
as a permit requirement we performed our monthly 8 hour composite samples on Tuesday 7/4/2023. Because this was a holiday the samples were held and composited on Wednesday 7/5/2023 to be taken to the lab. We take our required monthly e-coli sample just before leaving for lab to ensure shortest hold time possible. Wednesdays are normal weekly wasting days. (this wasting procedure is the pumping off of solids collected in bottom of primary clarifier to a sludge holding tank for later removal by permitted septage hauler). this wasting process creates a drop and then corresponding spike in flow when discharge returns, usually about 2000 gallons are wasted. The e-coli sample was taken during this spike in flow.    
   
HPV-YZW9-HQWZB