Facility Name:
|
Canaan
|
|
|
April Busfield Chief operator
|
|
|
Canaan
|
|
|
Houle Station Pump station 3
|
|
|
01/14/2021
|
|
|
01/14/2021
|
|
|
07:45 am to 08:15 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>100 to 1,000 gallons
|
|
|
Pump Malfunction
|
|
|
|
|
|
Manhole
|
|
|
Breakers fixed and remarked waiting for new starter solenoid other pump is running. Will be changing other one that is the same age when new one comes
|
|
|
Connetticut River
|
|
|
April Busfield Chief Operator
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
About 1.5 miles north of canaan on vt route 253 on left side of road. A starter solinoid malfunctioned on 1/13 and while we disconnected pump to order a new one and run backup a wrong circut breaker was tripped that shut off pump and callout softwear
|
|
|
|
|
|
HP5-RJ7R-TVPVJ
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|