View FacilityIncident Record


Facility Name: Brandon    
Stephen J. Cijka Chief Wastewater Operator    
Town of Brandon    
Wastewater Plant    
06/13/2024    
06/13/2024    
12:00 am to 08:30 am    
   
Discharged treated and partly disinfected effluent    
30000    
Chem Feed Problem    
None    
WWTF outfall    
turned up cl2 and so2 pumps on 6-13-2024 put cement blocks under flow meter sensor 6-15-2024 replaced chlorine pump head 6-18-2024    
Neshobe River    
Stephen J. Cijka Chief Wastewater Operator    
   
   
nForms    
Y    
   
   
   
658 am .30 mg/l cl2 .00 mg/l so2.115 MGD 410/100 e coli 735 am .30 mg/l cl2 .00 mg/l so2.034 MGD 820/100 e coli 830 am 8.80 mg/l cl2 .00 mg/l so2 .171 MGD 86/100 e coli    
   