Facility Name:
|
Brandon
|
|
|
Stephen Cijka
|
|
|
Town of Brandon
|
|
|
wastewater plant
|
|
|
01/04/2024
|
|
|
01/05/2024
|
|
|
06:10 am to 02:50 pm
|
|
|
|
|
|
Discharged treated and partly disinfected effluent
|
|
|
>500,000 to 1,000,000 gallons
|
|
|
High Flows
|
|
|
none
|
|
|
WWTF outfall
|
|
|
Cleaned chlorine contact chambers
Slide gate put in to prevent aeration effluent flow from backflowing into empty aeration tank.
|
|
|
Neshobe River
|
|
|
Stephen Cijka Chief Operator
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Endyne laboratory called that e coli count was 310 /100
from sample taken on 1-4-2024 at 610 am.
Chlorine residual leaving chlorine tank was 2.60 mg/l at 532,000 gallons per day. Design is 700,000 gallons per day.
|
|
|
|
|
|