View FacilityIncident Record


Facility Name: Brandon    
Stephen j. cijka Chief Wastewater Operator    
Town of Brandon    
500 Union Street Wastewater Effluent    
05/17/2022    
05/17/2022    
05:30 am to 11:00 am    
   
Discharged partially treated disinfected effluent    
>100,000 to 500,000 gallons    
High Flows    
   
WWTF outfall    
Aeration shut off to hold in solids chlorine and dechlor dosage rate doubled Aeration back on at 11 am The plant design flow was 700,000 gallons per day and we were getting 2,000,000 gallons per day    
Neshobe River    
David Atherton    
   
   
nForms    
Y    
   
   
   
Ground Saturated 2.58 inches rain on May 14 .08 inches rain on May 15 and 1.79 inches rain on May16 excess water due to ongoing infiltration/inflow problems    
   