Facility Name:
|
Brandon
|
|
|
Stephen J. Cijka Chief Wastewater Operator
|
|
|
Town of Brandon
|
|
|
Wastewater Plant
|
|
|
02/18/2022
|
|
|
02/18/2022
|
|
|
05:00 am to 07:00 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>100,000 to 500,000 gallons
|
|
|
Pump Malfunction
|
|
|
Pump Controller did not turn pumps back
|
|
|
Other
|
|
|
Reset pumps manually at pump controller cabinet and pushed auto button to each influent pump manually
|
|
|
Neshobe River
|
|
|
David Atherton Town Manager
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Pumps shut off on their own no alarm notification when entered at 645 am manhole in driveway inside gate bubbling raw sewage that flowed outside gate down berm into field which drains into drainage ditch that flows into neshobe river about 100 feet downstream of effluent discharge
|
|
|
|
|
|
HPF-JTWH-BXZ03
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|