Facility Name:
|
Brandon
|
|
|
Stephen Cijka Chief Wastewater Operator
|
|
|
Town of Brandon
|
|
|
Bottom land between Mill Lane and Conant Square
|
|
|
02/22/2018
|
|
|
03/07/2018
|
|
|
03:15 am to 12:00 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>1,000,000 gallons
|
|
|
Crack/Hole in Pipe
|
|
|
|
|
|
Other
|
|
|
REpresentative from Vermont Rural Water went with my assistant and found problem March 6. Assistant called public works director. Public works director called stream alterations ANR and local contractor .Also Godwin Pump called to bring 200 feet suction hose,400 feet discharge hose, and 6 inch self prime pump to pump between manholes. River water stopped going into sewer main. 40 feet hdpe pipe ordered
|
|
|
Neshobe River
|
|
|
Stephen Cijka Chief Wastewater Operator
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
12 inch ac pipe broke in 2 places along river between manholes
|
|
|
|
|
|