Facility Name:
|
Bethel
|
|
|
Tim Mills Utility Director
|
|
|
town of bethel
|
|
|
manhole at the junction of Rt.12 & Rt.107
|
|
|
05/22/2019
|
|
|
05/22/2019
|
|
|
09:15 am to 12:30 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>1,000 to 10,000 gallons
|
|
|
Other
|
|
|
none
|
|
|
Manhole
|
|
|
transported the raw wastewater by vactor truck from the pump station to the wastewater treatment plant until the force main cover was resealed.
|
|
|
white river
|
|
|
Tim Mills Utility Director
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
a sub-contractor for the AOT was rehabbing manholes on Rt. 12 in which they inadvertently disturbed an access cover to the force main line leading from the pump station to the wastewater treatment plant. a calculation was done using data from the effluent flow chart with an approximate loss of 2733 gallons.
|
|
|
|
|
|