Facility Name:
|
Brighton
|
|
|
Kean Galunas Chief Operator
|
|
|
Brighton
|
|
|
Cross St, Island Pond
|
|
|
03/05/2022
|
|
|
03/05/2022
|
|
|
08:00 am to 10:30 am
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
>100 to 1,000 gallons
|
|
|
Crack/Hole in Pipe
|
|
|
|
|
|
Stormwater collection system
|
|
|
Pump station shut down approximately 10:30 am with septic hauler called in to
bypass station for the duration of excavation and force main repair.
|
|
|
Clyde River
|
|
|
Rodger Sheldon - Project Manager Brighton WWTF
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
Force main break surfacing and going into storm drain
|
|
|
|
|
|
HPF-YQ4T-FJZJ8
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|