Facility Name:
|
Vergennes
|
Caller Name And Title:
|
Rick Chaput, Chief Operator
|
Municipality:
|
City of Vergennes
|
Location (street or site):
|
CSO# 002 Macdonough Dr. pumping station
|
Incident Start Date:
|
12/21/2018
|
Incident End Date:
|
12/21/2018
|
Incident Start End Times:
|
02:30 pm to 04:30 am
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Authorized Wet Weather CSO Overflow
|
Estimated Volume (gallons):
|
15,100 gallons
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
None
|
Waterbody Impacted:
|
Otter Creek below the falls in Vergennes
|
Contact Name And Title For Public:
|
Rick Chaput, Chief Operator
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
High flows caused by an intense rain storm on December 21, 2018 resulted in the discharge of a combination of sewage and stormwater from CSO#002. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
nForm Submission Number:
|
HNK-7GXD-5E31H
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|