Facility Name:
|
Vergennes
|
|
|
Rick Chaput Chief Operator
|
|
|
City of Vergennes
|
|
|
Below falls in Vergennes Macdonough Pump Station
|
|
|
02/03/2016
|
|
|
02/03/2016
|
|
|
12:40 pm to 05:10 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
20,100
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
Otter Creek
|
|
|
Rick Chaput Chief Operator 802 877-2931
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on Feb. 3rd 2016 resulted in the discharge of a combination of sewage and stormwater from Macdonough drive pump station. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
Rainfall 0.42"
|
|
|
|
|
|
2D3-3TZT-JMFA
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|