Facility Name:
|
Shelburne 1 (Crown Rd)
|
|
|
Walt Arsenault, Operator
|
|
|
Shelburne
|
|
|
Falls Bridge Pump Station
|
|
|
05/04/2018
|
|
|
05/04/2018
|
|
|
08:30 pm to 09:00 pm
|
|
|
|
|
|
Other
|
|
|
>10,000 to 100,000 gallons
|
|
|
Power Outage
|
|
|
None
|
|
|
Manhole
|
|
|
Immediately contacted two other Shelburne wastewater personnel, one to operate our tanker to capture excess wastewater and stopped any overflow. The other worked to repair transfer switch which he was able to get generator power to pump station.
|
|
|
The Laplatte River
|
|
|
Chris Robinson
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
When commercial power was lost due to severe storm in Shelburne, pump station emergency generator started as designed. However, transfer switch to accept generator power never switched over leaving pump station unable to operate for approximately one hour.
|
|
|
|
|
|
HND-JGR7-44RBV
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|