Waste Water Inventory Website
            Watershed Management Website Drinking Water Website Waste Management Website
View FacilityIncident Record


Facility Name: Shelburne 1 (Crown Rd)    
Walt Arsenault, Operator WWTF # 1    
Shelburne    
WWTF # 1    
02/22/2018    
02/24/2018    
04:45 pm to 12:00 am    
   
Discharged treated and partly disinfected effluent    
>100,000 to 500,000 gallons    
High Flows    
None    
WWTF outfall    
Chlorine delivery ratio was increased on 21 Feb 18. In addition, on 23 Feb 18, two E-coli samples, one from each SBR, will be captured during the decant process, and brought to Endyne Lab for E-coli analysis. Sample results will be relayed to Shelburne wastewater personnel no later than 24 Feb 18.    
Lake Champlain    
Walt Arsenault    
   
   
nForms    
Y    
   
   
   
Rapidly melting snow created high flow conditions that were outside the normal operating parameters of the facility. Increased flows potentially reduced disinfection time in chlorine contact tank. A chlorine residual of 1.30 mg/l was recorded along with the dispensing of 7.8 gallons of chlorine.    
   
HNB-T92G-5P2FH