Facility Name: St Albans City    
Caller Name And Title: Brian Willett Chief operator    
Municipality: City Of St. Albans    
Location (street or site): At the main wastewater plant    
Incident Start Date: 05/22/2024    
Incident End Date: 05/22/2024    
Incident Start End Times: 05:00 am to 07:00 am    
Estimated Duration Of Event:    
Nature Of Incident: Discharged partially treated disinfected effluent    
Estimated Volume (gallons): .234    
Cause Of Discharge: Mechanical Failure    
Type Of Obstruction:    
Point Of Discharge: WWTF outfall    
Corrective Action Taken: The electrician that does work for the city was called in and found the problem and corrected it. During the power outage the bypass was chlorinated and dechlorinated.    
Waterbody Impacted: Stevens Brook Lake Champlain    
Contact Name And Title For Public: Marty Manahan Director of Public works.    
Call Date:    
WW Staff Called:    
Type Of Notification: nForms    
Public Overflow Report For Web: Y    
   
   
   
Description Of Incident: There was a power outage in the area. When the power went out the transfer switch on the generator did not switch over . The Electrician was brought in and the problem was corrected. Between the power outage and the generator issue the power was out for approx. 2 hours. During the power outage the Bypass was Chlorinated and dechlorinated.    
   
nForm Submission Number: HQ3-TDTS-23KJK