Facility Name:
|
Rutland
|
|
|
Tyler Harte, Lab Technician
|
|
|
City of Rutland
|
|
|
CSO # 3 School Street & CSO # 4 Meadow Street - Combined - Third Base Ball Field
|
|
|
05/29/2026
|
|
|
05/29/2026
|
|
|
10:02 pm to 10:26 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
39200
|
|
|
High Flows
|
|
|
none
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
East Creek
|
|
|
Robert Protivanky, Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 5-29-2026 resulted in the discharge of a combination of sewage and stormwater from CSO # 3 School Street & CSO # 4 Meadow Street - Combined - Third Base Ball Field . This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HQN-YAG3-2QBPR
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|