Facility Name:
|
Rutland
|
|
|
Mark Breznick / Lab. Director
|
|
|
City of Rutland
|
|
|
CSO # 5 - West Street Siphon
|
|
|
12/19/2025
|
|
|
12/19/2025
|
|
|
12:24 pm to 12:37 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
20800
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
East Creek
|
|
|
Robert Protivansky, Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by unusually warm temperatures, rapid snow melt and steady rain that fell at a maximum rate of 1.92 Inches per hour, and a total accumulation of 0.63 inches on 12/19/2025 resulted in the discharge of a combination of sewage and storm water from CSO # 5 - West Street Siphon. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|