Facility Name:
|
Rutland
|
|
|
Mark Breznick / Lab Director
|
|
|
City of Rutland
|
|
|
CSO #3 - School Street
|
|
|
03/26/2021
|
|
|
03/26/2021
|
|
|
03:24 pm to 03:39 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
10,106 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
East Creek
|
|
|
James Rotondo, Interim Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by heavy rain that fell for a short period of time at a rate of 1.45 inches per hour with a total accumulation of 0.35 inches on 3/26/2021 resulted in the discharge of a combination of sewage and stormwater from CSO #3 - School Street. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HP7-H5BX-8SWGJ
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|