Facility Name:
|
Rutland
|
Caller Name And Title:
|
Calvary Cemetery
|
Municipality:
|
City of Rutland
|
Location (street or site):
|
CSO #1 - Calvary Cemetery
|
Incident Start Date:
|
03/26/2021
|
Incident End Date:
|
03/26/2021
|
Incident Start End Times:
|
03:53 pm to 04:28 pm
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Authorized Wet Weather CSO Overflow
|
Estimated Volume (gallons):
|
10,390 Gallons
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
None
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
None
|
Waterbody Impacted:
|
Otter Creek
|
Contact Name And Title For Public:
|
James Rotondo, Interim Commissioner of Public Works
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
High flows caused by heavy rain that fell for a short period of time at a rate of 1.45 inches per hour with a total accumulation of 0.35 inches on 3/26/2021 resulted in the discharge of a combination of sewage and stormwater from CSO #1 - Calvary Cemetery. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
nForm Submission Number:
|
HP7-H50V-WWGCQ
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|