Facility Name:
|
Rutland
|
|
|
Mark Breznick / Lab. Director
|
|
|
City of Rutland
|
|
|
CSO # 3 - School Street & CSO # 4 - Meadow Street - Combined - Third Base, Ball
|
|
|
05/01/2020
|
|
|
05/01/2020
|
|
|
03:41 pm to 04:33 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
15,337 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
East Creek
|
|
|
Jeff Wennberg, Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by heavy rain that fell at a rate of 0.33 inches per hour, and with a total accumulation of 0.49 inches on 5/1/2020 resulted in the discharge of a combination of sewage and stormwater from CSO # 3 - School Street & CSO # 4 - Meadow Street - Combined - Third Base, Ball Field . This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HNZ-EKTR-ZKG4N
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|