Facility Name:
|
Rutland
|
|
|
Mark Breznick / Lab Director
|
|
|
City of Rutland
|
|
|
CSO # 5 - West Street Siphon
|
|
|
09/23/2019
|
|
|
09/23/2019
|
|
|
07:58 pm to 08:28 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
16,107 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
East Creek
|
|
|
Jeff Wennberg, Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by heavy rain that peaked at a rate of 0.89 inches per hour and a total accumulation of 0.53 inches on 9/23/2019 resulted in the discharge of a combination of sewage and stormwater from CSO # 5 - West Street Siphon. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HNT-0YK8-FPY9K
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|