Facility Name:
|
Rutland
|
|
|
Jeffrey Wennberg, Commissioner
|
|
|
Rutland City
|
|
|
East side of East Creek near River Street Pumping Station
|
|
|
08/07/2019
|
|
|
08/07/2019
|
|
|
01:30 pm to 02:00 pm
|
|
|
|
|
|
Discharged untreated sewage
|
|
|
Estimated 63,000 gallons
|
|
|
Crack/Hole in Pipe
|
|
|
|
|
|
Crack/hole in pipe
|
|
|
The first leak was contained on the ground and the area limed. When the second leak occurred the force main was taken offline. The system is now operating with a single force main, which reduces the hydraulic capacity of the system by 6.5 MGD during wet weather.
|
|
|
East Creek
|
|
|
Jeffrey Wennberg, Commissioner
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
This leak was on the failing 1972 force main that connects River Street pump station with the treatment plant. The City has moved aggressively to replace this pipe following a leak and repair last year, and the City hopes to have the replacement in service by the end of November. Early Tuesday morning another leak occurred near the one repaired last year. Upon discovery the force main was taken offline. No untreated sewage reached receiving waters during this event. The failed section of pipe was repaired around 1:00 PM today. When the main was pressurized to test the repair another leak opened up at East Creek on the pump station side. That leak was discovered after about 30 minutes when the main failed to pressurize.
|
|
|
|
|
|
HNR-VJWA-68DE1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|