Facility Name:
|
Rutland
|
|
|
Mark Breznick / Acting Lab Director
|
|
|
City of Rutland
|
|
|
CSO # 3 & CSO #4 - School & Meadow Streets Combined - Third Base Ball Field
|
|
|
04/15/2019
|
|
|
04/15/2019
|
|
|
01:54 am to 05:07 am
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
2,261,691 gallons
|
|
|
High Flows
|
|
|
None
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
East Creek
|
|
|
Jeff Wennberg, Commissioner of Public Works
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm that totaled 2.14 inches in 1.5 hours on 4/15/2019 resulted in the discharge of a combination of sewage and stormwater from CSO #3 & CSO #4 - School & Meadow Streets Combined- Third Base Ball Field. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|