Facility Name:
|
Rutland
|
Caller Name And Title:
|
Rod Munroe / Lab Director
|
Municipality:
|
City of Rutland
|
Location (street or site):
|
CSO #1 - Calvary Cemetery
|
Incident Start Date:
|
12/28/2018
|
Incident End Date:
|
12/28/2018
|
Incident Start End Times:
|
01:04 pm to 04:14 pm
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Authorized Wet Weather CSO Overflow
|
Estimated Volume (gallons):
|
556,653 gallons
|
Cause Of Discharge:
|
High Flows
|
Type Of Obstruction:
|
None
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
None
|
Waterbody Impacted:
|
Otter Creek
|
Contact Name And Title For Public:
|
Jeff Wennberg, Commissioner of Public Works
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
Steady rain that totaled 0.66 inches in less than 6 hours, along with melting ice and snow in roadways caused high flows on 12/28/2018. Which resulted in the discharge of a combination of sewage and storm water from CSO #1 - Calvary Cemetery. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings. In addition, during this event, 2,427,007 gallons of urban storm water were treated through the wastewater treatment facility before returning it to the environment.
|
|
|
nForm Submission Number:
|
HNK-D5AT-M43HK
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|