Facility Name:
|
Middlebury
|
|
|
Dean Rheaume, Operator
|
|
|
Middlebury
|
|
|
206 Lucius Shaw Lane- S/N 013 Pump Station No.17- Main Pump Station
|
|
|
06/18/2026
|
|
|
06/18/2026
|
|
|
03:44 pm to 05:32 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
75000
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
None
|
|
|
Otter Creek
|
|
|
Emmalee Cherington, Director of Engineering
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on June 18,2026 resulted in the discharge of a combination of sewage and stormwater from CSO 12 . This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|
HQP-DFRC-ND6VK
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|