Facility Name:
|
Middlebury
|
|
|
Jeremy Rathbun Wastewater Superintendent
|
|
|
Town of Middlebury
|
|
|
Treatment Plant
|
|
|
05/31/2025
|
|
|
05/31/2025
|
|
|
08:30 pm to 09:00 pm
|
|
|
|
|
|
Discharged partially treated disinfected effluent
|
|
|
200000
|
|
|
High Flows
|
|
|
|
|
|
WWTF outfall
|
|
|
The operators are modifying the control for Automated Storm Mode to try to prevent it from activating unless absolutely necessary. This will be done within the week.
|
|
|
Otter Creek
|
|
|
Jeremy Rathbun Wastewater Superintendent
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
They Automated Wastewater Control System put the plant into storm mode. This resulted in flows beyond those designed for the plants UV disinfection system, and the possibility of partially treated discharge
|
|
|
|
|
|
HQD-1XWT-ZAK8Z
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|