Facility Name:
|
Middlebury
|
|
|
Robert Wells, Middlebury Wastewater Superintendent
|
|
|
Middlebury
|
|
|
206 Lucius Shaw Lane - Main Pump Station
|
|
|
09/11/2023
|
|
|
09/11/2023
|
|
|
08:00 am to 02:15 pm
|
|
|
|
|
|
Other
|
|
|
>100,000 to 500,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
Reached out to our plant inspector to see if there is any other action they would suggest to take beyond waiting for our pumps to come back from repair due to the flood on August 3rd..
|
|
|
Otter Creek
|
|
|
Robert Wells, Middlebury Wastewater Superintendent
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
The bypass pump is able to pump 1.6 million gallons and with the recent rains is not able to keep up with the amount of wastewater coming in.
|
|
|
|
|
|
HPX-JSEP-CAE6V
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|