View FacilityIncident Record


Facility Name: Middlebury    
Robert Wells, Wastewater Superintendent    
Middlebury    
206 Lucius Shaw Lane Main Pump Statin    
09/03/2020    
09/04/2023    
03:00 pm to 09:00 am    
   
Discharged untreated sewage    
>100,000 to 500,000 gallons    
Mechanical Failure    
   
Combined sewer overflow structure    
Changing out bypass pump with different one. Complete on 9/4/23 about 8:50 AM    
Otter Creek    
Robert Wells, Middlebury Wastewater Superintendent    
   
   
nForms    
Y    
   
   
   
Knock sensor failure on the bypass pump. Pump is running but very low and not keeping up with the flow. Sensor will not be available until either late Tuesday or early Wednesday. Replacement pump coming tomorrow to swap out. Crew and Crane set to swap it out. Swapped out the Bypass pump this morning and was complete and running about 8:50 AM.    
   
HPX-CQZV-DG0R8