Facility Name:
|
Burlington River
|
Caller Name And Title:
|
Nathan Lavallee Chief Operator North and East Plants
|
Municipality:
|
Burlington
|
Location (street or site):
|
Intersection of Colchester Ave and Barrett
|
Incident Start Date:
|
06/18/2024
|
Incident End Date:
|
06/18/2024
|
Incident Start End Times:
|
12:20 pm to 01:46 pm
|
Estimated Duration Of Event:
|
|
Nature Of Incident:
|
Discharged untreated sewage
|
Estimated Volume (gallons):
|
8800
|
Cause Of Discharge:
|
Obstruction/Blockage
|
Type Of Obstruction:
|
rags
|
Point Of Discharge:
|
Combined sewer overflow structure
|
Corrective Action Taken:
|
Removed blockage, additional line cleaning scheduled.
|
Waterbody Impacted:
|
Winooski River
|
Contact Name And Title For Public:
|
Matt Dow
|
Call Date:
|
|
WW Staff Called:
|
|
Type Of Notification:
|
nForms
|
Public Overflow Report For Web:
|
Y
|
|
|
|
|
|
|
Description Of Incident:
|
While contractor was working on their monitoring equipment, a ball of rags dislodged from the equipment which plugged the line downstream.
|
|
|
nForm Submission Number:
|
HQ4-FT53-JAF14
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|