Facility Name:
|
Burlington River
|
|
|
Matthew Dow, Wastewater Facilities Manager
|
|
|
City of Burlington
|
|
|
Colchester Ave CSO
|
|
|
07/25/2018
|
|
|
07/25/2018
|
|
|
09:28 pm to 09:47 pm
|
|
|
|
|
|
Authorized Wet Weather CSO Overflow
|
|
|
>10,000 to 100,000 gallons
|
|
|
High Flows
|
|
|
|
|
|
Combined sewer overflow structure
|
|
|
none
|
|
|
Winooski River
|
|
|
Megan Moir, Div Head Water Resources
|
|
|
|
|
|
|
|
|
nForms
|
|
|
Y
|
|
|
|
|
|
|
|
|
|
|
|
High flows caused by an intense rain storm on 7/25/2018 resulted in the discharge of a combination of sewage and stormwater from the Colchester Ave. CSO. This is an authorized discharge intended to protect the sewer system, to prevent overflows from other parts of the sewer system, and to prevent backups into homes and other buildings.
|
|
|
|
|
|